SUNDAY 17 DECEMBER - OBAN - The Loco Release Line will be redesignated No 1 Platform Line and the trap points at the exit removed. The 3-lever ground frame controlling access to No 1 Platform Line will become a 4-lever ground frame.

The hand operated connection between the No 1 Platform Line and the Down Sidings will be repositioned 45 yards further from the Station, with the Down Sidings end becoming trap points, and will be controlled from the 4-lever ground frame.

The Stop Board on No 1 Platform Line will be repositioned 80 yards nearer the Station. A new Stop Board worded "STOP, OBTAIN TOKEN AND PERMISSION TO PROCEED" will be provided at the exit from the Down Sidings.